| Trigger
| Notification Message Sent |
| Scheduled Start |
Day of scheduled start. |
| Scheduled Complete |
On the 7th, 4th, and 2nd day before, and on the date of scheduled completion. Days
can be configured as desired by the System Admin in Configuration table. |
| Start Past Due |
On the 1st, 2nd, 4th, and 7th business day after scheduled start if
the user did not put an appropriate date in the actual start date field, on or before the scheduled start date. Days
can be configured as desired by the System Admin in Configuration table.
|
| Completion Past Due |
On the 1st, 2nd, 4th, and 7thbusiness day after scheduled completion
if the user did not put an appropriate date in the actual completion date field, on or before the scheduled completion date.
Days
can be configured as desired by the System Admin in Configuration table. |
| Anticipate Start |
On the 7th, 4th, and 2nd day before scheduled start. Days
can be configured as desired by the System Admin in Configuration table. |
| Predecessor Complete |
On the day a user enters an actual completion date for a predecessor task. (must be identified as such in workplan
column) |